Investments in renewable energies 2026 – Three Legislative Projects Shaping Wind Energy Investments in Poland

Introduction

The year 2026 is set to mark an important regulatory phase for onshore wind energy investments in Poland. Following years of criticism regarding lengthy planning procedures, limited grid access and regulatory uncertainty, the legislator has introduced three separate legislative projects which, although developed independently, may jointly have a significant impact on wind energy investments.

These include: UD332 (spatial planning and Integrated Investment Plan – ZPI), UC84 (grid connection reform, Sejm print No. 2150) and UC118 (procedural amendments to the Renewable Energy Sources Act).

Spatial planning and ZPI – Project UD332

Project UD332, prepared by the Ministry of Climate and Environment, focuses on the planning stage of wind energy investments.

Key measures include:

  • enabling onshore wind projects to be located based on an Integrated Investment Plan (ZPI),
  • aligning public consultation rules with general spatial planning regulations,
  • allowing parallel planning and environmental procedures.

The minimum setback distance of 700 metres from residential buildings remains unchanged. The project is currently at the governmental stage.

Grid connection – Project UC84 (Sejm Print No. 2150)

Project UC84 reforms the grid connection process for renewable energy installations, aiming to release blocked grid capacity by eliminating so-called “zombie projects”.

The proposal includes:

  • shortening the validity of grid connection conditions from 24 to 12 months,
  • increasing the connection prepayment to PLN 60/kW,
  • introducing additional fees and financial securities,
  • linking grid connection rights to specific project milestones.

While the objective is broadly supported, the project remains controversial. Parliamentary work has been temporarily suspended.

Procedural streamlining under the RES Act – Project UC118

Project UC118 introduces amendments relevant to onshore wind energy, including:

  • maintaining the 700-metre minimum setback distance,
  • harmonising planning and consultation procedures,
  • allowing a more flexible approach to distances from power grids, reflecting technological progress,
  • clarifying local community participation mechanisms, including virtual prosumer models.

The project aims to shorten investment timelines without altering sensitive distance regulations. It remains at the governmental stage.

Conclusion

Although UD332, UC84 and UC118 address different stages of the investment process, they share a common goal: improving the efficiency of onshore wind energy investments in Poland.

Our experts continuously monitor these legislative developments and advise investors throughout the planning, implementation and management of renewable energy projects.

Share this article

You may also be interested in these articles:

current, Investment and commercial law
25.10.2026

SP. Z O.O. EXPLAINED – MEANING, LEGAL FORM, DIFFERENCES FROM GMBH

A limited liability company (sp. z o.o.) is a business form that continues to enjoy enduring popularity in Poland among both new and experienced entrepreneurs. Thanks to the advantageous combination of limited liability for shareholders and relatively low entry barriers, a sp. z o.o. offers an attractive alternative to other types of companies and sole proprietorships.

Read article
current
22.10.2026

Quo vadis, Polish-German relations? On trust, tensions and a shared future

On 15 October 2026, VON ZANTHIER & DACHOWSKI hosted the conference “Quo vadis, Polish-German relations?” in Poznań. Participants from Poland, Germany and other countries discussed the history of relations between the two countries, their current state and what the future may hold.

Read article
current, Investments in renewable energies
22.10.2026

Grid Connection First – Grid Connection Conditions, Deadlines and Technical and Contractual Safeguards

Access to the grid is increasingly decisive in determining whether an onshore wind project in Poland can be developed and financed. The new rules change the process for obtaining connection conditions by introducing additional fees, security requirements and shorter deadlines, while also creating new flexible connection models. We explain what these changes mean for investors and which risks should be considered at the project planning stage.

Read article